Hi Experts,

       I am new to APO, i am trying to transfer ECC routing (task list type N) to APO, but i am unable to find that, i have transferred work centers and materials of that routing to APO successfully but i am unable to find PPM of my product, what might be the problem.

thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jun 20, 2013 at 09:37 AM

    Hi Devidas,

    Please check following;

    1) If your production version is error free in material master,

    2) Validity dates in production version and PPM integration model are matching.

    Please check and let me know if you still face any issue.

    Rgds

    Sourabh

    Add comment
    10|10000 characters needed characters exceeded

    • Hello,

           Thanks for quick response, i was doing all the transfer in one go thats why i was unable to do, because of your guidance i have done in sequence and i can see PPM in APO now, thanks all of you, points rewarded, i am closing the thread.

      Regards,

      Devidas Karad