The Add-on installation terminated during phase XPRA_EXECUTION with error code 0008

Hello All,

I am applying ADD-ONE packages for  FINBASIS and SEM-BW  with Tco SAINTon ERP EHP6  on HP-UX .

The Add-on installation terminated during phase XPRA_EXECUTION WITH ERROR:

The following details help you to analyze the problem:


    -   Error in phase: XPRA_EXECUTION

    -   Reason for error: TP_STEP_FAILURE

    -   Return code: 0008

    -   Error message: OCS Package SAPK-605IRINSEMBW, tp step "R",
        return code 0008

Her is log file from  SAINT: Action log of queue:

  Import phase 'XPRA_EXECUTION' (18.06.2013, 14:09:18)
  Error during executing the tp command 'tp XPA ALL RIS ...'
  tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
    This is tp version 380.07.22 (release 720, unicode enabled)
    Warning: Parameter DBLIBPATH is no longer used.
    standard output from tp and from tools called by tp:
  Details of the error situation can also be found in the import logs
  Interrupt the import due to an error situation (18.06.2013, 14:09:22)
  Display detailed informations concerning the error in phase 'XPRA_EXECUTION'
  Abort the import due to an error situation (18.06.2013, 14:09:48)

Post-import method FINB_TR_AFTER_IMP_METHOD started for FBLC L, date and time: 20130618140919
Efterbehandling Client Cascade sprunget over for klient 000
Transport Tool FINBASIS: Client Cascade startet for klient 001
Egnet RFC-destination kunne ikke findes
Transport Tool FINBASIS: Client Cascade afsluttet for klient 001
Transport Tool FINBASIS: Client Cascade startet for klient 010
Egnet RFC-destination kunne ikke findes
Transport Tool FINBASIS: Client Cascade afsluttet for klient 010
Errors occurred during post-handling FINB_TR_AFTER_IMP_METHOD for FBLC L
FINB_TR_AFTER_IMP_METHOD belongs to package FINB_TRANSPORT_TOOL
The errors affect the following components:
    FIN-FB (Financials Basis)
Post-import method FINB_TR_AFTER_IMP_METHOD completed for FBLC L, date and time: 20130618140919
Post-import methods of change/transport request SAPK-605IRINSEMBW completed
      Start of subsequent processing ... 20130618140918
      End of subsequent processing... 20130618140919

And:


Post-import methods for change/transport request: SAPK-605ITINSEMBW
    on the application server: sapux24

Post-import method FINB_TR_AFTER_IMP_METHOD started for FINB_LOCAL_CONTENT T, date and time: 20130618140919
Efterbehandling Client Cascade sprunget over for klient 000
Transport Tool FINBASIS: Client Cascade startet for klient 001
Egnet RFC-destination kunne ikke findes
Transport Tool FINBASIS: Client Cascade afsluttet for klient 001
Transport Tool FINBASIS: Client Cascade startet for klient 010
Egnet RFC-destination kunne ikke findes
Transport Tool FINBASIS: Client Cascade afsluttet for klient 010
Errors occurred during post-handling FINB_TR_AFTER_IMP_METHOD for FINB_LOCAL_CONTENT T
FINB_TR_AFTER_IMP_METHOD belongs to package FINB_TRANSPORT_TOOL
The errors affect the following components:
    FIN-FB (Financials Basis)
Post-import method FINB_TR_AFTER_IMP_METHOD completed for FINB_LOCAL_CONTENT T, date and time: 20130618140919
Post-import methods of change/transport request SAPK-605ITINSEMBW completed
      Start of subsequent processing ... 20130618140919
      End of subsequent processing... 20130618140919

Execute reports for change/transport request: SAPK-605ITINSEMBW
    on the application server: sapux24

**************************************************

Reports for change/transport request SAPK-605ITINSEMBW have been executed
      Start of................ 20130618140919
      End of.................. 20130618140919
EXECUTION OF REPORTS AFTER PUT
end date and time   : 20130618140919
exit code           : 8

Any idea or advice.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jun 18, 2013 at 01:03 PM
    10

    Hi Ejersbo,

    Could you try repeating the phase as most of the XPRA errors are cleared with repeating the phase.

    Regards,

    Deepak Kori

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 04, 2013 at 08:31 AM

    Hi Ejersbo,

    when upgrading several problems have to be solved:

    1. The system is disabled for all users by the upgrade. Only DDIC and SAP* may login.

    2. You cannot restart the system during upgrade. This is necessary to reset the password in client 001.

    3. The users SAP*, DDIC are not allowed to create new programs in workbench SE80.

    Solution:

    1. Unlock the system by running a cmd command on the SAP server:

    tp unlocksys <SID> pf=D:\usr\sap\trans\bin\TP_DOMAIN_<SID>.PFL

    Please replace <SID> with your system ID and check the path to your tp profile.

    2. Log on with a development user to you productive client and check that DDIC is unlocked and you know the password.

    3. Write a new program ZCOPYUSER with SE80:

    REPORT zcopyuser.

    DATA gs_usr02  TYPE usr02.

    START-OF-SELECTION.
      SELECT SINGLE * FROM usr02 INTO CORRESPONDING FIELDS OF gs_usr02
                      WHERE  bname = 'DDIC'.

      gs_usr02-mandt = '001'.
      MODIFY usr02 CLIENT SPECIFIED FROM gs_usr02.

    4. Run the program ZCOPYUSER

    5. Create a RFC connection to client 001 with user DDIC - Transaction SM59

    6. Register the RFC connection with transaction FINB_TR_DEST.

    7. Continue with the upgrade.