on 06-17-2013 2:00 PM
Hi SAP PM Experts,
How to activate issue plant in Component overview of task list. What is the use of field issuing plant(PSWRK) in component overiew of task list ? Can we create reservation of material for different plant by assinging issuing plant field value ?
Regards
Maheboob
Please use for all PM related queries.
@ Maheswaran - You are one of the top contributor of EAM/PM forum, you very well know that PM related queries are handled in that forum, whenever you see such PM related questions in this forum, either you suggest the OP to post in EAM forum or report to moderator to move it to appropriate forum, So that all PM related informations will be available at one space, it will help others to search and look solution at one place, not two different area. This is for other contributors also.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Appreciate your thought.
I have insisted to open thread in appropriate space for many threads. But, sometimes it can't be avoided by having cross threads.
In PLM space, you can find threads related to PM, QM, etc., as well. So, its authors responsibility to find suitable space to open their thread.
By default, Issuing Plant will be Maintenance Planning Plant. If you want to have different plant as issue plant, you can change the issue plant & reservation can be created.
Even in Task list, you can assign the material with different plant so that that particular component can be issued from that plant.
For example, Equipment is being located in Plant A. So equipment master, BoM & Task list will be created against Plant A. But one of the spares will be consumed from Plant B. In this case, that material would have been created for Plant B only in MM01 & it would not have been extended to Plant A. In that case, you can use that Plant B material for Plant A equipment.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Maheswaran,
Let me make the requirment more clear,
1. General task list is created for Planning Plant : 1001
2. Material is maintained & stocked in Plant : 1004
Unable to assign the material of Plant 1004. Giving the Error Message "Material XXXXXXX is not maintained in Plant 1001.
I Can't extend this material to Plant 1001. Because stock is maintained in Plant 1004. There is not stock in Plant 1001
Requirement is to create Material reservation in Plant 1004 but not to Plant 1001
Have you configured anything different as I am getting the same error message as NOOR NABI MAHABOOB BASHA. Task List Plant and Material Plant must be the same in our system.