MRP Run based on material reservation and material type.

former_member382397
Participant
0 Kudos

Dear Experts,

I have a requirement to run MRP two ways.

MRP(Type 1) run for those materials, which need to maintain minimum stock. This is solved by changing MRP type to VB, and maintaining minimum stock level.

but the second requirement is, need to run MRP based on material reservation.

Requirement is, once the material reservation created from the maintenance order. When i run MRP ( Type 2), it should check all materials in the reservations, and available quantity in that plant. Basing on the requirement it should create PRs automatically.

I have followed through http://scn.sap.com/thread/1571481 . By Mr. Maheswaran. But could not follow the procedure. Can any one please explain.

Best regards,

Anil.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos
  1. Create New Material
  2. Assign MRP type as PD
  3. Create one Maintenance Order for that material
  4. Reservation will be created
  5. Now run MRP in MD02 for that material
  6. It will generate PR

Get the inputs from your PP / MM consultants on maintaining the MRP view data in Material Master, in MD02 & Configuration for MRP run.

Answers (2)

Answers (2)

former_member382397
Participant
0 Kudos

Dear Maheswaran and Ajit.

Thank you very much for reply.

ajitkumar
Active Contributor
0 Kudos

you may maintain MRP type PD and lot size EX. if you are having safety stock requirement, you may also indicate the proportion of safety stock available for planning in config  MRP > Planning > stocks>