on 06-12-2013 9:29 AM
Hello Everyone !!
I am facing a problem in Sap & Primavera features. Actually in SAP PS we have WBS length 24 chr but in Primavera it is 20 chr . How can i export from Sap to Primavera because Prmavera allow me only for 20 chr .
Thanks & Regards,
Yogesh Acharya
Hi Yogesh Acharya,
Solution for above issue i.e.
In Primavera p6, In Enterprise menu you have an option in Activity codes.In which you select SAP WBS Element and click on modify and change the max length in it as 24 then your SAP WBS starts working from SAP PS to Primavera.
Thanks,
Venkat Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Yogesh,
You can try the following options:
1) In P6, you can create a UDF at each WBS level which will match
exactly to SAP WBS_ELEMENT data and use this for mapping.
2) or if SAP WBS_ELEMENT includes SAP Project id then you can remove
this project id before transferring to P6 to reduce length of WBS.
3) or in P6 restrict WBS to 20 char only - to match length WBS_ELEMENT
field of SAP.
4) or maintain WBS mapping xml file that will give you P6 WBS based SAP
WBS_ELEMENT data. Read this file in workflow for WBS mapping.
i.e. P6 WBS = corresponding SAP WBS_ELEMENT.
Best Regards,
Brendan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.