Hi,
We have an issue where when the TR is created after material staging the quantity of the material is 0.
As per standard SAP, kindly let me know how the system calculates the materials availability when creating the TR. The quantity is defined during the Process Order creation.
The Destination Storage bin is Dynamic storage bin and therefore the question of "quantity reduction" (fixed bin) is not there.
Also I checked the stock in the system, and when I test with less stock the Order itself does not release and gives the error of parts missing.
Any suggestions of how the TR is created after WM Material Staging.