Dear Guru,
I have created few master data like material,location,resource,BOM (not a phantom one) ,Master recipe. I am able to cif all master to APO except master recipe.
All masters are are appearing in APO. I tried with both as PPM and PDS to cif, but i can not see it in APO.
I checked the Master recipe in ECC and itis showing no error. During CIF also there is no error appearing in both ECC(CFG1) and APO(SLG1), CQ monitor.
My Master recipe (MR) contains one operation and one phase.
I have done some general check:
1.Active integration model for product,location ,and Bom,recipe - all IM are active.
2.Validity of Recipe - up to year 2099
3.Machine time is maintained in recipe.
4. Control key in resource contains scheduling.
5.I have used only machine capacity i.e.008.
6.capacity formula and scheduling formula are both same.
7.BOM is active.
Note: My resource is a single mixed resource.
Guys, i am creating the Master recipe for the 1st time. Basically do not have enough idea on process industry.
Is there any configuration setting exist for PPM/PDS in APO or ECC system. which is missing in my case.
What are the other reason which can be in this case.
Thanx & regards
Kishor