APO PPDS Optimizer Not Scheduling Orders For Same Product Together

66 Views

All,

Here is my situation. I have two products (P1 and P2) assigned to the same setup group (meaning no setup when switching between these 2 products). These two products can be produced on the same machine (M1). What I an finding is that when I run the optimizer it may schedule orders for these two products as follows:

I have 3 orders for 100 each for P1

I have one order for 200 for P2.

Sequence of orders on M1 is 100 P1, 100 P1, 200 P2, 100 P1.

Ideally the optimizer should schedule all the orders for the same product together as follows:

Sequence of orders on M1 should be 100 P1, 100 P1, 100 P1, 200 P2.

Is there a way to get the optimizer to scheule all the orders for the same product together even if there are multiple products in the same setup group? I don't want to define material level setup transitions to accomplish this. Thanks for the help