on 06-07-2013 1:15 PM
Hi experts,
We are looking for the settings for capacity loading at free period automatically while creating planned order /production order / sales order.
kindly suggest us what are all the settings that are required in configuration and in master data.
Thanks in advance
Hi Raj
What you are looking for is the capacity availability check. This is available for production or process orders.
Take a look on the following note for more details:
160613 | Capacity check: Capacity availability check |
You will also find useful information on SAP Help:
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you very much Caetano for your guidance,
Could you please guide which settings will support that function. How will system will look for the free available period. whether system will look for free period considering only previous load or will it consider the current production order load.
Is this facility available during planned order creation facility itself.
Thanks in advance.