Hi All,
I am facing the issue while trying to do delivery from Project via CNS0.
The business requirement is:
1-Subcontractor needs to manufacture the finished product.
2-Few componenets needs to either procured from externan vendor and few are sent from warehouse to Sub contracting vendor.
3-After completion of the Finished product, we are doing GR
4-Then it is expected to carry out delivery from project stock
Could anyone one suggest what is the best way to do it ?
Current procedure and issue
i am creating a Subcontracting PR in Me51n and PO and GR against the WBS.
Then i can see the project stock at WBS but not able to deliver via CNS0
In CNS0 it says, no item selected.. it means CNS0 is expecting 281 movement type and it is not happening.
Could you suggest how can we do it ...thanks a lot in advance !!!
//Ashis