Hi Experts,

We are facing the one issue in the process order.The planned cost and actual cost are pink wrongly in internal activities like labor (Plan cot is 150 actual cost is 450 but its worng values in the system.correct value is 250. we are not useing the routing. and what is process order is settled ?step by step and t.codes?