on 06-06-2013 10:20 AM
Hi experts,
Can anybody suggests what are all the reports we can get to help the MRP controller.
Some of the requirements are as below:
1. MRP controller want to know the shortages list.
2. MRP controller wise delivery details. He want to know how many requirements are there for him and how many of them delivered and how many pending requirements still there for him.
3. He want to know to Planning the products( sales orders which are already exist) based on the available components in stores.
he will prioritize the production for Sales orders requirements based on FIFO model considering the available stocks only.
Thanks in advance.
Hi,
Use MDVP Report.& Pls. follow the link -
http://scn.sap.com/thread/1470238
Revert if useful.
Regards,
Milind
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Raj
I suggest you to check transactions MD06 and MD07.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI raj,
In SE11, table MARC,
Plant- WERKS and MRP controller DISPO, it will display all the materials with MRP controller.
othere wise you can check all require data from COOIS report.
TnX
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raj,
You can use CO24-Missing Parts Information System . Delivered quantity can be checked in COOIS.
Regards,
Jeewana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.