How to maintain original planned date in project system

former_member143179
Participant
0 Kudos

To get project monitoring/analysis related information , we have a business requirement of  maintaining the original planned date and the revised date (so called scheduled date , determined by the sap system during project scheduling) .

I request the forum members to guide me as how to maintain the original planned date .

With Thanks and Rgds

B Mittal

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

The project progress analysis, and all the relative infomation regarding scheduling of Basic date/Early Start and End dates and Latest dates can be feteched by the CNE5 progress report .

I hope this might suits your requirement.

Regards,

vrkumar

former_member203098
Active Contributor
0 Kudos

you can try project versions, where you can create a version (sanapshot of existing project)

in txn cn71/cn72 at the time project rescheduling. we can compare these versions with scheduled dates.

regards,