Skip to Content
0
Former Member
Jun 03, 2013 at 02:01 PM

How to bring PM03 external service details to duration and number

113 Views

Hi ,

We want to use PM03 both for scheduling and external service procurement in order operations. In external service details , I put helper supply , welder supply in service description and give qty as 2 nos , unit as day , gross rate as 10 USD /per day .

In standard SAP PM03 is not meant for scheduling. However based on the unit and quantity used (in above case unit is Day and quantity is 2 nos for helper and same for welder), sap defaults work (it assumes Day means 24 Hrs ...Thus it calculates 24 X 2 X2 =96 Hrs) against operation number

Is there any way we can default this data into duration and number in operation and force system to calculate work ? Also how can we configure the system to assume Day=8 Hrs not 24 Hrs ?

I know there is no config for above requirement ....