Dear experts,
We configured standard monthly billing for contracts.
But we noticed following behaviour by sap:
If the contract start date is in the last 3 days of the month, the next settlement date is counted backward in next month. E.g.
Contract starts on 2013.05.29
Billing cycles are:
2013.05.29 - 2013.06.27
2013.05.28 - 2013.07.28
What we are expecting is:
2013.05.29 - 2013.06.28
2013.05.29 - 2013.07.28
Is there any configuration can influence this behaviour? And how to handle Feb (28 days / 29 days)?