on 05-30-2013 3:53 PM
Hi,
We have a scenario where we have to bill the customer for partially completed operation in Service order through DP90 and still the service order is in Released state as we have some more operations to confirm
To COPA, the corresponding Revenue has been updated but not the Actual cost associated for that
As i know, in standard the cost will be updated only when we do TECO ( please correct me if it is wrong)
now my user asking to see the corresponding cost of partially created invoice in COPA, please let me know if it is possible in standard or do we need to use any exit
Thanks in advance
regards,
santosh
Hi
You need to do RA (Results Analysis) based on sales revenue in your service order
for that, the revenue =must be posted on your service order
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Costs will happen before revenue happens!
Regards
Waza
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.