Hi,

We have a scenario where we have to bill the customer for partially completed operation in Service order through DP90 and still the service order is in Released state as we have some more operations to confirm

To COPA, the corresponding Revenue has been updated but not the  Actual cost associated for that

As i know, in standard the cost will be updated only when we do TECO ( please correct me if it is wrong)

now my user asking to  see the corresponding cost of partially created invoice in COPA, please let me know if it is possible in standard or do we need to use any exit

Thanks in advance

regards,

santosh

Accepted Solutions (0)

Answers (2)

Answers (2)

ajaycwa1981
Active Contributor
0 Kudos

Hi

You need to do RA (Results Analysis) based on sales revenue in your service order

for that, the revenue =must be posted on your service order

br, Ajay M

Former Member
0 Kudos

Costs will happen before revenue happens!

Regards

Waza

former_member186385
Active Contributor
0 Kudos

Hi ,

thanks for your reply, can i see the cost in COPA for partial invoice?

regards,

santosh

Former Member
0 Kudos

I am not an expert here, but do have EK01 in the service order?

Regards

Waza