on 05-28-2013 7:03 PM
Hi All,
I have a requirement as below:
if prod supervisor is 'X' (assignment tab) and GL account is 'Y'
(settlement rule) in a prodcution order ....system should default this GL to
cost center "Z". we have 12 combinations like this.
So i have maintained same in OKC9 but system is not validating and
defaulting to cost center which i maintained in OKB9.
Kindly advise how to overcome this issue.
Your suggestions will be rewarded with points.
Thank you.
Regards,
raja lucky
Hi
They system give priority on OKB9, You have to remove the cost center in OKB9 and you have the apply Note 392273.
Thanks.
S.Sivakumar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Substitutions during settlement are restricted. Please, consult
Note 392273 - When is validation/substitution called?
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.