cancel
Showing results for 
Search instead for 
Did you mean: 

Update HU in ECC from eWM

Former Member
0 Kudos

Hi all,

I need to replicate HU split or repack in ECC when this is done in eWM.

Anyone, did something like that?

Any advice will be appreciated.

Thanks.

Gianni Canetti

Accepted Solutions (0)

Answers (1)

Answers (1)

JuergenPitz
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

there is a customizing setting "Control Message Processing Dependent on Recipient". You can enter the "HU Parameters" for you EWM inbound delivery to "Report HU Data". But as far as I can see this only works until the GR posting is sent back to ERP or even only when you change the HU on the GR staging area.

Brgds

Juergen

Former Member
0 Kudos

Hi Juergen,

thanks for your answer.

This setting is already in place in our system but the requirement is to replicate in ERP the full life HU history while is managed into EWM.

thanks anyway.

Gianni

JuergenPitz
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

this is not possible. And why would you want to do that?

Brgds

Juergen

Former Member
0 Kudos

Hi Jurgen & Gianni,

I have similar problem.

Scenario is Inbound processing with repacking at workcenter.(storage process involved)

At ID, I am creating a dummy HU  e.g. A001 for product A1 100kg. This will unloaded using WT and GR is posted automatically. ECC is updated with GR and HU A001. (as expected through std settings)

The HU is then taken to workcenter using HUs WTs.

At work center, the product will be repacked into two new HUs  B001 and B002  50 kg each. then these are putaway into final bins.

problem is-- when repacking happens,  HU A001 is deleted from EWM whereas it is still there in ECC with status (PHEX WHSE).

The new HUs B001 and B002 are created in just EWM but not in ECC.

This way.. 100 kg in ECC is with one HU A001  and  same 100 kg in EWM is with  HUs B001 and B002.

This seems inconstitent update of systems.   How to make sure that HUs are consistent in both systems. I want the two new Hus to be replicated in ECC and original dummy HU to be deleted from ECC.

JuergenPitz
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

"I want the two new Hus to be replicated in ECC and original dummy HU to be deleted from ECC."

Won't work. And why would you want this? The new HUs have no relationship to the old delivery anymore. This is also not a question of consistency. One is you warehouse system, this knows HUs, the other is your stock keeping system, where you just now how much material you can sell.

Brgds

Juergen

Former Member
0 Kudos

Thanks Juergen. Clear now.

Is there any setting through which I can prevent GR posting upon unloading completion?

Former Member
0 Kudos

Hi Santosh,

There was a discussion on this in the past. See Juergen's response as well.

https://scn.sap.com/thread/3353900

Regards,

Shashidhar