dates are not calculated

Dear frends,

I have created one materai with following details,

MRP1: mrp type pd, lot size:ex, mrp controler:000

MRP2: inhous production:5, GR processing:4. Schedule margin key:001

mrp3:strategy :40

MD61:27.05.2013:5 qty

when i run the MRP with sheduling 1. system calculate the dates below.

order start date:03.06.2013

finish date:04.06.2013

please tell me how system calculate these dates.

from my point of vivew these dates are wrong which are calculated by sytem.

please correct me

Thanks

Manoj

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on May 27, 2013 at 01:14 PM

    Dear Kumar ,

    The Dates are calculated as per the scheduling parameters (Basic Scheduling & Lead Time Scheduling )Please check your Scheduling Settings

    Regard's

    Tallha

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 27, 2013 at 01:19 PM

    Hi Manoj

    Can you please check if the lead time scheduling was executed for this planned order?

    If this is the case, the tab 'detailed scheduling' should be created for this order and the basic start date was probably changed according to the setting 'adjust basic dates' for the scheduling parameters (OPU5). I understand that you are running MRP with scheduling 1, however, if the order was already lead time scheduled before, MRP will still use lead time scheduling.

    Otherwise, check if you have a lot size dependent in house production time on the tab work scheduling.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Caetano,

      Thanks for reply.This planned order don't have any lead time scheduling.First time i ran the mrp with basic data scheduling 1.

      Please tell me what is the wrong.

      Please tell me the procedure how to calculate the dates with example.

      Based on that i will run one scenarion .

      Thanks

      Manoj

  • author's profile photo Former Member
    Former Member
    Posted on May 28, 2013 at 04:53 AM

    Hi,

    Pls. check 'In-house' production lead time in Material master , Schedule Margin key (i.e. floats defined ) & dependent orders completion dates(Availability of respective SFGs /RMs )

    Revert if useful.

    Regards,

    Milind

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.