on 05-23-2013 10:03 AM
Hi Experts,
Our client is maintaining MRP Type: VM (Autromatic reorder point plng). We maintain a re-order point and maximum stock level in the material master. Based on my knowledge of MRP runs, when a material stock reaches below the re-order point, MRP should created a planned order (we use planned orders instead of direct PR creation) with a proposed amount to satisfy the maximum stock level. MRP also takes into account already created PRs or POs and it will not create planned orders if there are enough stock levels. Upon MRP Run - MD01, our material which already had a PO incoming, did not delete an existing planned order it had.
My material has a re-order point of 3, with replenish to maximum stock level of 6. Current stock was 1, so doing the math, MRP created a planned order for 5. Meanwhile, a PO was created for this same item with a qty of 15 (exceeding the maximum stock). Why didn't the planned order disappear upon MRP run? If it helps, at my Stock/Requirements List (MD04), my planned order has an exception message of 07 and my PO has an exception message of 20.
I would like to discuss this matter more in detail if need be, thank you!
Hello Paolo
Exception 20 for a firmed element usually means that this is outside the rescheduling horizon or it is not included on the rescheduling check at all.
I wrote a WIKI about the rescheduling check, already refered by Senthil on this thread.
The following note may also be useful:
1745312 | MRP creates redundant proposals though there are fixed future receipts which ca |
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Please check the following before you run MRP in MD01 or MD03 :
1.Check the planned order as it should not be Firmed ( should not be marked with STAR symbol in MD04) .This happens if you changes anything in planned order like dates or mark the firming indicator in change mode of planned order
2.Check the Re-scheduling Horizon days as defined and the day you are running MRP , number of days you have defined in material master as Fwd , Bwd periods , indicator in Material Master MRP3 view .
3.While running MRP in MD02 or MD01 , please select as planning mode as 3 - Delete and Re-create planning date .
4.Please check the Total Receipt in MD04 as well as total requirement ( un firmed planned order , PR, PIR , SO,STPR)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paolo
What is your delivery date in production order. Is it within the tolerance level of Rescheduling horizon. Actually as per exception message 20, the date of GR for the material is outside of tolrance level and system is asking you to delete the production order as it is not required.
Regards
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
While scheduling MRP, set the variant for planning mode to '3' "Delete and recreate the planning data".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Experts,
Inserting images for clarification,
This is Stock Requirements screen for my item.
This is the MRP details of the material.
As seen, a PO with 15 order quantity has been created, yet the planned order of 5 will still not go away after MRP run.
Is there a way to bypass the date check?
Thank you all.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If its un-firm planned order ( Check MD12-Planned Order -Firm check box marked or not ) , then while re-planning( Select or running MRP in MD02 or MD03 with Planning Mode -3), it should will be nullified with available stock , fixed receipt and total demand qty .Apart from that you can also try to make use of Consumption Mode ( Bwd/Fwd ) in MRP3 view based on the periods ( Bwd& Fwd consumption period) .
Dear Paolo,
It seems planning time fence must be set either at material level or MRP group level, and normally the firmed planned order does not gets changed during the planning run.
So check if the firming indicator is set for these procurement proposal. Remove this and then re run MRP keeping planning mode 3and check the results.
Best Regards,
Amit Kataria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What is your delivery date in production order. Is it within the tolerance level of Rescheduling horizon. Actually as per exception message 20, the date of GR for the material is outside of tolrance level and system is asking you to delete the production order as it is not required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paolo,
Please check the Rescheduling Horizon set in OMDW; and if needed, adjust/increase the no. of days
Pls refer to the following links as well -
https://help.sap.com/saphelp_45b/helpdata/en/b4/7055967935d1118b3f0060b03ca329/content.htm
http://wiki.sdn.sap.com/wiki/display/ERPMan/What+is+rescheduling+and+how+does+it+work
Regards,
Senthil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.