How to Assign Standard Milestone to Std netowrk

Dear PS experts,

It seems assigning Standard Milestone to Std netowrk is not possible. Kindly confirm that it is only possible to assign milestones in Cj20n traxn to project.

Thanks

Jatin

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 21, 2013 at 01:01 PM

    When you are in CN01 / CN02, choose the corresponding activity and then from Menu bar, choose Activity --> Milestone Overview. Here you can maintain the same.

    Regards,

    Bala.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.