What will happen after transfer of requirement to mrp?

Hi experts,

The availbility check carries out in sales order in particular plant level.If It is finds negetive ATP quantities,system follows the forwarding schedules and confirms the quantities on after requested delivery date.And transfore the requirement to mrp.my question is we dont know how much time required to produce the material how system gives the confirm date after requsted delivery date?plese explain after transfore the requirement to mrp in production side?

Thanks&regards

krishna mohan

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 23, 2013 at 03:45 PM

    Hi KM,

    Please check the setting 'Check without RLT' in Availability Checking Control (OVZ9).

    The F1 help details for this setting could explain.

    Regards,

    Senthil


    1.JPG (123.6 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.