cancel
Showing results for 
Search instead for 
Did you mean: 

QM Order

former_member369043
Participant
0 Kudos

Hi All,

How to calculate cost for QM from QM Order? How does aprisal cost and defect cost will be calculated? Do I need to create separate QM order?

With Regards,

Neel

Accepted Solutions (1)

Accepted Solutions (1)

former_member184536
Active Contributor
0 Kudos

hi

Yes you have to create two separate order i.e for apprasail cost and second for non-conformity cost. Otherwise how will you differentiate that  cost invested in doing inspection and cost occurs in rectifying the defects.....

Please go through below links

http://help.sap.com/saphelp_media464/helpdata/en/e4/e312d81ff611d4b2cd0050da4ceab0/frameset.htm

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/QMCOST/QMCOST.pdf

regards

Manish

former_member369043
Participant
0 Kudos

Thanks Manish,

Neel

Answers (1)

Answers (1)

Former Member
0 Kudos
former_member369043
Participant
0 Kudos

Thanks Sujit,

It helped me.

Neel,