Hi all
I have a requirement where client is asking for a Planning Calendar where he can set the deadlines for specific processes to finish thru out the planning process and wants to track the progress of each. Is there any way I can achieve this, I am not sure where I can have the planned submit date in the BPF.
-SM
Hi Swati,
What you are asking for is basically milestone planning, and BPC is not meant for that. However, there can be certain customizations to do this. But I dont think its worth doing too many customizations for this purpose.
I believe you should try not to accept this requirement.
Hope this helps.