Implementation of End2End Project uisng SAP ME.

Former Member
0 Kudos

Dear Experts,

I have few doubts about implementing E2E project using SAP ME 6.0.

1. Generally after configuring Shop floor master data, How we'll transfer the configuration data(System Rules, Shop floor data), from Dev to Quality and Quality to Production. Is it Site to Site Transfer?

2.Moving of  WIP and ODS databases, Is it Export and Import of DBA commands?

3.What else needs to be moved from Dev to Quality and Quality to Production apart from master data & Databases?

4. Perfoming unit testing?

5.How we move customized extensions?

Would be greateful if someone could share the links or documents which will give me the over all idea of  the above details.

Thanks in advance.

Eshwar.

Accepted Solutions (1)

Accepted Solutions (1)

MiguelSanchez
Explorer
0 Kudos

Hello Eshwar,

To transfer the configuration data you can use the Configuration Data Transfer Export / Import activity. Here you can decide which business objects you want to transfer. You can not transfer transaction (SFCs, shop orders) data with that.

For you customized extensions with ME SDK, you have to deploy the extensions on each system.

Best Regards,

Miguel

Former Member
0 Kudos

Hello Miguel,

Thanks for the reply.

Answers (0)