Skip to Content
1
May 16, 2013 at 04:27 AM

Budget Check, while SC creation

81 Views

Hello Experts,

We are on SRm 4.0 Classic scenario.

We will be implementing funds managemnet in ECC backend.

I want to understand few things with this respect:

1) If we dont activate Funds management at SRM, is there any way, for eg: DOC CHECK BADI, with the help of which I can do budget check against IO/CC in the backend, and prohibit SC creation if sufficient budget is not available? (Throw error message etc)

2) Do SRM 4.0 CLASSIC scenarion support Funds Managment activation at SRM end?

I have already gone through few SCn links, but still want some clarity specific to this scenario of ours.

Thanks,

Dhananjay