Dear Sir,

When i take MRP ,Coverage profile is considered and planned order are correctly created as per calculation .

But i have some change in my PIR(MD62) and take MRP again for same product -but system this time not considered Coverage profile.

Please provide solution for this to consider coverage profile in Re MRP

We are taking MRP by MD01.

And Scanario is Make to Stock having Strategy group 10

Regards,

Sumit