Simple Remove Gaps in schedule giveng by PPDS Optimizer

Former Member
0 Kudos

Hello
Dear Colleagues, I'm using the PP/DS Optimizer to cschedule with good results, but I need to
remove small time gaps that the solution of the optimizer didn't resolved.

(I have no restrictions that could result in these gaps )

I have tried to remove this gaps with the standard reschedule heuristic SAP001 "Schedule Sequence Heuristic" but it takes in to account
just the parameters of the Heuristic changing the sequence that the Optimizer gave, I also have tried using the SAP003 Schedule Sequence Manually but it only gives me an schedule error.

Basically I want to maintain optimizer sequence but enhance it by removing not desired gaps  by the simplest way.

Thank you for your help,

Gonzalo García

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Gonzalo,

Try to use heuristic SAP_DS_01 "Stable Forward Scheduling".  It may be too performance intensive for your needs but its worth a try.  You can also try increasing the weighting of Makespan in the optimizer profile.  Good luck!

Best Regards,

Mike

Former Member
0 Kudos

Hello
Maclean, I tried with both options, using SAP_DS_01 with several scenarios
moves the sequence so I tried increasing weighting of Makespan and it gave the
desired results.

Thank You,

Former Member
0 Kudos

Hi Gonzalo,

I'm glad to hear that you were successful.

Best Regards,

Mike

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Gonzalo,

   In PPDS Optimizer the results depends on weightage you give to each objective functions, for eg., if your optimizing horizon is for four weeks and you dont have enough orders to be fully scheduled for four weeks , in the optimizer results you might see gaps in between depending on the weightage you gave. So it is always wise you give some weigtage to makespan(but not more than setup time or setup cost) when you dont have enough orders for the whole optimization horizon.

Rgds,

Kiru

dev_shetty
Active Participant
0 Kudos

Hi Gonzalo,

                   Please try with setting"compact scheduling" in basic setting of the optimizer profile.

Thanks

Dev