Hi All ,
I want to change start event that trigger workflow in to other .
How to change from one event to other , when i tried two steps are being created .
Please help .
Thanks and Regards,
Sijin K P
go to transaction swdd
then press ctrl+f8
after that go to start event tab
then from there u will be able to change it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can get the answer from the Google search itself.
Anyway Go to header of the workflow you can add or remove events under events tab.Make sure tat your binding tat element inside the workflow.
Event---->Workflow Binding.
Once you changed the event then activate it.(It will automatically create linkage in SWETYPV transaction)
Warm Regards,
Ragav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You can change it in PFTC, under "Triggering events".
What do you mean by "two steps are being created"? Where?
regards
Rick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
10 | |
10 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.