Dear Gurus;
I'm using BCV reports in SAP PPM v5.0, but BCV doesn't update the changed information in Project Management.
Someone can fix this? or change some time of update info?
Thank you.
Best regards.
Mariano
Hello Mariano,
By default BCV shows the information that the first time the query was executed ( the information is saving in cache for 1 hour), You can change this behaviour ( 2 options) :
1. IMG -->Cross Application Components -->Process and tools for enterprise Applications -->BCV -->Query Management -->Maintain Query Cache
2. Enter user parameter /BCV/QRM_SKIP_CACHE = X ( all users)
I implemented option 2 and the problem was solved.
I hope this can be useful.,
Regards,
Clara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.