How to fetch follow on order in SAP PM.

Can we remove maintenance item from Maintenance plans once equipment status set inactive.

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi,

You cannot remove the Item, if it is 1:1.

Instead you can set the Maintenance Plan status Inactive and deletion flag set.

Regards

Terence

SPG24
Explorer
0 Kudos
Hi Thank you
SPG24
Explorer
0 Kudos
If maintenance plan have one maintenance item and have multiple object lists, if we set the Maintenance Plan status Inactive and deletion flag, it will any impact
MTerence
Active Contributor
0 Kudos
Inactive is set at maintenance plan, it will not schedule.